Checklist Before Issuing a Fit-out BOQ or Tender
A checklist before you issue a fit-out BOQ or tender in Dubai: drawings, line items, joinery, provisional sums, exclusions and how bidders should reply.
What to check before issuing a fit-out BOQ or tender: drawings, structure, line items, joinery, provisional sums, exclusions, commercial terms and return format.
Short answer: before issuing a fit-out BOQ or tender, check that the drawings are current and complete, every item has a clear specification and unit, provisional sums are labelled, inclusions and exclusions are written down, the landlord's conditions and working hours are attached, and every bidder receives exactly the same package and return format. Gaps in the BOQ become gaps between quotes.
A bill of quantities turns drawings into a priced list. A clear BOQ lets you compare contractors line by line; a loose one produces quotes that look similar but price different things. Use this checklist before the tender goes out.
1. Drawings and documents
- Drawing register with current revision numbers
- Layout, reflected ceiling, finishes and joinery drawings
- MEP and fire and life safety drawings where systems change
- Specification or finishes schedule
- Landlord or mall fit-out guide and design criteria
- Site survey or existing-condition drawings
If the drawings and the BOQ disagree, say which one takes priority.
2. Structure of the BOQ
Organise the BOQ so contractors price the same way:
- Preliminaries and general requirements
- Demolition and strip-out
- Partitions and walls
- Ceilings
- Flooring
- Wall finishes
- Doors, ironmongery and glazing
- Joinery, item by item
- MEP works
- Fire and life safety works
- Signage and specialist items
- Provisional sums and allowances
3. Each line item
| Check | Why |
|---|---|
| Clear description | Avoids different interpretations |
| Drawing or detail reference | Links the line to what is drawn |
| Unit (m, m², nr, item) | Makes rates comparable |
| Quantity, or "to be measured by bidder" | States who carries the risk |
| Material named by brand and code, or "or approved equivalent" | Stops silent downgrades |
| Finish and fire rating where relevant | Often missed, often costly |
4. Joinery lines
Joinery is the hardest part to describe in a BOQ. Price each piece as a separate item with a reference to its elevation and section, and state the core board, finish, edge detail, hardware range and any integrated lighting. A single line for "reception desk" without drawings will produce very different prices. See the joinery shop drawings checklist.
5. Provisional sums and allowances
Use provisional sums only for items that are genuinely not yet designed. Label them clearly, give the same amount to every bidder, and ask for the contractor's overheads and profit on them separately. Too many provisional sums make the tender less certain.
6. Inclusions and exclusions
Write down who provides each of these:
- Landlord and authority fees and deposits
- Loose furniture and appliances
- IT, AV and security systems
- Kitchen equipment
- External signage
- Design and consultant fees
- Temporary utilities on site
7. Commercial terms
- Form of contract and payment terms
- Retention and defects liability period
- Programme requirements and key dates
- Working hours and access restrictions
- Insurance requirements
- Validity period of the quote
8. Return format
Ask every bidder to return:
- The priced BOQ in your format, without changes to descriptions
- A list of assumptions and exclusions
- Alternatives as separate options, not in the base price
- A programme showing key stages and dependencies
- Lead times for long-lead materials
Common BOQ mistakes
- Lump-sum lines with no quantities
- "As per drawing" with no drawing reference
- Materials described loosely ("timber finish", "stone")
- Missing preliminaries
- MEP left out, or described in one line
- Different bidders receiving different drawing revisions
Questions
What is the difference between a BOQ and a scope of works?
A scope of works describes what is included in words. A BOQ breaks that scope into measured, specified items so each can be priced and compared.
Who prepares the BOQ for a fit-out?
Usually the consultant or a quantity surveyor appointed by the client. On design-and-build projects, the contractor may prepare it.
Should contractors be allowed to change the BOQ?
They should price it as issued and list any errors, assumptions or alternatives separately. Otherwise quotes are no longer comparable.
How do I compare quotes from a BOQ tender?
Line by line. Look for missing items, unusually low rates, long exclusions lists and qualifications, not only the total. See what drives fit-out cost in Dubai.
How Prastara prices a BOQ
At Prastara we check each BOQ line against the drawings before pricing and return a list of discrepancies and assumptions with the quote, because a BOQ that disagrees with its drawings is the most common source of variations later. See turnkey fit-out, submit a BOQ or how to choose a fit-out contractor.
Send drawings for a priced proposal.