Restaurant Fit-out in Dubai: The Sequence From Drawings to Opening
How a Dubai restaurant fit-out runs from drawings to opening: kitchen layout, MEP coordination, hygiene finishes, landlord steps, site works, inspections.
The usual sequence of a restaurant fit-out in Dubai, from kitchen layout and MEP coordination to hygiene finishes, landlord steps, inspections and opening.
Short answer: a restaurant fit-out in Dubai usually runs from concept and kitchen layout, through landlord and authority submissions, detailed drawings and kitchen equipment coordination, to procurement and fabrication, site works, inspections and handover. The kitchen drives the sequence: its layout, extraction, drainage, gas and power must be fixed early, because they shape MEP, finishes and submissions.
Restaurants are among the most coordinated fit-outs. The dining room is what guests see, but the kitchen, services and hygiene requirements decide the programme. This guide sets out the usual sequence in general terms; requirements differ by location and change over time, so check current requirements with the landlord and the relevant authority.
1. Brief, concept and kitchen layout
Start with the menu and operating model, because they decide the kitchen. A kitchen consultant or equipment supplier usually prepares the kitchen layout and equipment schedule. At the same time, the interior designer develops the front-of-house concept, seating plan, bar and service areas.
Fix early:
- Kitchen layout and equipment list with power, water, drainage and gas needs
- Extraction and fresh-air requirements
- Seating capacity and layout
- Bar and back-bar layout
- Toilets and staff areas
2. Landlord and authority requirements
Ask the landlord or mall for the fit-out guide before design develops. Restaurants usually need the landlord's acceptance of the design, and authority steps such as food safety and fire and life safety, often beginning with the kitchen layout. Dubai Municipality, free zone authorities and Civil Defence may each be involved depending on location. See fit-out approvals in Dubai.
3. Detailed design and MEP coordination
The design team turns the concept into construction drawings. For restaurants, coordination is critical:
- Kitchen hood and extraction ductwork routes
- Grease traps and drainage falls
- Gas supply and detection, where gas is used
- Power for equipment and lighting
- Fire suppression over cooking equipment
- AC and fresh-air balance between kitchen and dining room
Overlay the kitchen equipment drawings with the ceiling and MEP drawings to find clashes before they reach site.
4. Hygiene finishes
Food areas need finishes that are durable, easy to clean and suitable for wet conditions:
| Area | Typical requirements |
|---|---|
| Kitchen floors | Slip-resistant, impervious, coved skirting, falls to drains |
| Kitchen walls | Smooth, washable, impervious surfaces |
| Kitchen ceilings | Washable, moisture-resistant |
| Food preparation counters | Stainless steel or other food-safe surfaces |
| Bar and service joinery | Moisture-resistant cores, sealed edges, durable tops |
| Dining room | Hard-wearing finishes that suit the concept and cleaning routine |
Confirm current hygiene requirements for your location before finalising finishes.
5. Shop drawings and samples
The contractor prepares shop drawings for joinery, bar counters, banquettes, screens, ceilings and specialist items, and submits material samples. Approving these promptly keeps fabrication on programme.
6. Procurement and fabrication
Kitchen equipment, lighting, furniture and imported finishes can have long lead times, so order them as soon as drawings and samples are approved. Joinery and bar counters can be made off site while the site is prepared, which reduces work inside an operational mall.
7. Site works
A typical order on site: strip-out and setting out, MEP first fix, partitions and ceilings, wet areas and kitchen finishes, MEP second fix, joinery installation, kitchen equipment installation and connection, decorative finishes and lighting, then cleaning.
8. Testing, inspections and handover
Test and commission the services, including extraction, fire suppression and gas where present. Authority and landlord inspections follow, and the restaurant can open only once the required certificates and permits are issued. Allow time for snagging, staff training and a trial service.
Checklist before construction starts
- Kitchen layout and equipment schedule fixed
- Extraction, drainage, gas and power coordinated with MEP
- Landlord fit-out guide received and design accepted
- Authority submissions planned for your location
- Hygiene finishes chosen and confirmed
- Long-lead items ordered after drawings are approved
- Programme includes inspections and a trial service
Questions
What usually delays a restaurant fit-out?
Late kitchen layouts, clashes between extraction and other services, and resubmissions to the landlord or authorities. Fixing the kitchen early helps most.
Who designs the restaurant kitchen?
Usually a kitchen consultant or the equipment supplier, coordinated with the interior designer and the MEP engineer.
Can the dining room be built before the kitchen design is final?
Some work can proceed, but services, ceilings and the bar often depend on the kitchen, so starting early can mean rework.
Who issues the permits for a restaurant?
The landlord or mall, and the relevant authorities for the location. The contractor prepares drawings and coordinates submissions; the permits and certificates are issued by those bodies.
How Prastara builds restaurants
We deliver restaurant fit-outs and make the bar counters, banquettes and joinery in our own workshop in Jebel Ali. At Prastara we ask for the kitchen equipment schedule before we price a restaurant, because extraction, drainage and power routes change the ceiling and joinery details. See hospitality fit-out, Pizza Express JLT and Poli restaurant in Downtown Dubai.
Send drawings for a priced proposal.